A licensed deck contractor builds a new deck in a fairly fixed order. Eagle Mountain Decks, a referral service, connects you with that contractor, and this page walks the job from first measurement to final inspection so you know what to ask.
The stages, in order
Your contractor may combine or reorder some of these.
- Design and measuring. Size, height off the ground, which door it serves, stairs, and where the posts land.
- Drawings and permit application. In Eagle Mountain the application goes to the Building Department through the city's online permit portal as PDF files.
- Footings. Holes are dug and concrete is poured under each post.
- Footing inspection.
- Framing. Posts, beams, the ledger on the house, then joists.
- Framing inspection.
- Decking, stairs and guards.
- Final inspection.
That is the usual order, not a city schedule. The Building Department, at 801-789-6614, can tell you which inspections your deck gets.
Step 1: Confirm the permit
The Eagle Mountain building page says building permits are required for all attached decks, or for those 30 inches or more above grade. A submittal includes the application, the deck checklist, building plans, any required engineering, and a site plan with setback measurements.
The city's deck checklist says documents go in as PDF files to the online portal to begin plan review. Questions go to buildinginspections@eaglemountain.gov or the permit handout number, 801-789-6614. Rules and fees change, so confirm there. The full walk-through is on the permits page.
Step 2: Understand the footings
The footing is the concrete under each post. Dig day is hard work, and shallow footings let frost move a deck.
- The city's Building Division design criteria set frost depth at 30 inches.
- The city's deck checklist says plans must show footings at least 30 inches deep.
- Sources: the city's design criteria and deck checklist.
Confirm the footing depth with the Building Department at 801-789-6614, because rules change.
Utility lines come first. Blue Stakes of Utah 811 asks to be notified at least 3 business days before any excavation, and digging deck footings counts. The service is free and required by law (Blue Stakes of Utah). Ask the contractor who places that request and when it went in.
The code also requires footings for a deck attached to a frost-protected house to be protected from frost, for example by going below the frost line (a third-party copy of the code (UpCodes)). Ask how deep the footings will go and how the depth will be shown to the inspector. Footings carry the whole structure, so they belong to a licensed contractor, with drawings and an inspection behind them.
Step 3: Ask how the ledger will be attached
The ledger is the board that ties one side of the deck to the house, and it is one of the things an inspector looks at.
- A third-party copy of the 2021 code (UpCodes) says a deck ledger may not be supported on stone or masonry veneer.
- The same page says ledgers must be flashed so water does not reach the house band joist.
- Have the contractor describe the fasteners and the flashing in plain words. If the answer is vague, ask again.
Ledger work is structural, so the steps stay with the licensed contractor and the city inspector.
Step 4: Check the materials against the engineering
For the frame, pressure-treated lumber is the usual choice. The USDA Forest Products Laboratory notes that deck lumber is usually pressure treated with a preservative or a naturally durable wood such as redwood or western redcedar (source).
For the surface, the main choices are pressure-treated pine, cedar, redwood, composite and PVC. The composite and PVC page covers the last two. Price differences are on the cost page.
Snow matters here too. The city's design criteria give no single snow figure for residential work. They say the ground snow load is determined with the Utah State University snow load website. Ask the contractor what load the plans use, especially if a hot tub or a roof might come later.
Step 5: Ask about engineering
The city's deck checklist states that all decks require structural engineering. A separate prescriptive sheet from the same office says decks of significant height and complexity may require a structural engineer. Because the two sheets differ, ask the contractor what engineering is in the quote. Sources: the checklist and the prescriptive sheet. Confirm which applies with the Building Department at 801-789-6614, because rules change.
Step 6: Ask these questions before you sign
- Will you apply for the permit and schedule the inspections? The city says inspections are scheduled by email and are not booked until the department sends a confirmation (building page).
- Is your license current in Utah's lookup? Look it up yourself.
- Can you hand over a liability insurance certificate? DOPL requires a license applicant to carry at least $1,000,000 per incident and $2,000,000 total (source), but ask for the actual certificate.
- How deep are the footings, and how will the ledger be flashed?
- Will the contract be in writing? The state publishes an optional Residential Construction Agreement.
Common questions
Can a low deck skip the permit?
Only under narrow terms. The city's handout says a deck is exempt only if it is not more than 30 inches above grade at any point and needs no guardrails, Utah's statewide amendment adds that it must not serve the required exit door (Utah Code 15A-3-202), and the building page says all attached decks need a permit. The Building Department can say which applies to yours before you plan around an exemption.
How close to the property line can a deck go?
Zoning sets setbacks. The city asks for a site plan showing setback measurements, so ask the contractor to check the zone for your lot.
Who builds the deck?
A licensed local contractor does. Use the contact page when you want a match.
Where these numbers come from: the city's deck checklist, the Division of Professional Licensing pages and the other sources linked above, all read in November 2026.