The short answer
Remodeling magazine's 2025 Cost vs Value report, published by the Journal of Light Construction, puts a wood deck addition in Salt Lake City at a job cost of $18,503 and a composite deck addition at $25,324. They are Salt Lake City market figures, not an Eagle Mountain quote, so a real price moves with your house.
| Deck type | Job cost | Resale value added | Cost recouped |
|---|---|---|---|
| Wood deck addition | $18,503 | $9,650 | 52.2% |
| Composite deck addition | $25,324 | $10,016 | 39.6% |
Source: JLC Cost vs Value 2025, Salt Lake City.
Step 1: Read the gap between wood and composite
- Composite costs $6,821 more than wood in that report.
- Composite adds $10,016 of resale value and wood adds $9,650.
- Wood recoups the bigger share of its cost, 52.2% against 39.6%.
For wood, the same report shows 52.2% recouped in Salt Lake City, against 97.3% for the Mountain region and 94.9% nationally. The Salt Lake City figure is the lowest of the three, so do not count on a deck paying itself back at sale. Build it for the way you will use it.
Step 2: See what moves a quote in Eagle Mountain
Run down this list with each contractor. The city items on it come from Eagle Mountain's own sheets; confirm them with the Building Department at 801-789-6614, because rules change.
- Engineering. The city's deck checklist says all decks require structural engineering, while its prescriptive deck requirements say decks of significant height and somewhat complex nature may require a structural engineer. Ask whether engineering sits inside the quote or on top of it.
- Footings. The same checklist asks for footings at least 30 inches deep, matching the 30-inch frost depth in the city's building design criteria, a design figure rather than a forecast. More posts or a taller deck means more concrete.
- Snow and wind loads. The city says the ground snow load comes from the Utah State University snow load website, and lists 100 to 105 mph for residential design wind (design criteria).
- Height. Eagle Mountain's prescriptive deck sheet says a deck more than 30 inches high must have a guard. See stairs and railings.
- Surface. Wood or composite. See composite and PVC.
- A roof. A cover or pergola changes the structure. See covered decks.
- Taking out an old deck. See rebuild and repair.
Step 3: Add the permit and plan review line
Eagle Mountain's consolidated fee schedule sets the building permit fee by project valuation. It starts at $24 for the first $500 and adds $3 for each additional $100 in the next bracket, plus a 1% state surcharge. The residential plan review fee is 40% of the permit fee.
The schedule works by valuation rather than by deck, so the permit line on your quote follows from the job's value. Ask the contractor to show that line and the plan review line separately. Fees change, so ask the Building Department at 801-789-6614 what applies.
Step 4: Add the cost of keeping it up
The job cost covers building. The years afterward cost something too.
- TimberTech says a wood deck typically needs cleaning, sanding and staining every one to two years (source). TimberTech sells composite, so weigh the source.
- The Journal of Light Construction says clear sealers last a year or two, and semisolid stains can last as long as five years (source).
- TimberTech says composite decking has a 25-to-30-year life span (source). Trex offers limited residential warranties of 25 to 50 years (source).
A limited warranty has terms, so ask what it covers.
Step 5: Compare quotes side by side
- Have each contractor price the same size, height, surface and railing.
- Ask whether the permit, engineering and inspections are inside the number.
- Get the board brand and joist spacing in writing.
- Check each license in Utah's lookup.
- Ask for a written agreement. The state publishes an optional Residential Construction Agreement.
A price far below the rest may leave something out, so ask what.
Step 6: Get a real number
Eagle Mountain Decks is a referral service, so it cannot quote a price. Ask for a match on the contact page, then ask the licensed contractor you are connected with to price your actual house. The permit side is covered on the deck permits page.
Common questions
Does a small job still need a licensed contractor?
Utah Code 58-55-305 exempts alteration, repair or addition work with a contracted value under $7,000, labor and materials included (source). Ask any contractor whether they are licensed anyway.
Why is composite so much more?
Composite boards cost more up front, and each board line comes with its own spacing and fastener rules. Any saving shows up later, in less cleaning and refinishing.
Where these numbers come from: the 2025 Cost vs Value report for Salt Lake City, the city's fee schedule and deck checklist, and the sources linked above, all read in November 2026.