The Eagle Mountain Building Department issues and approves deck permits. Eagle Mountain Decks, a referral service that connects homeowners with licensed local contractors, cannot do either, so this page follows the process as the department publishes it.
Who to contact
- Office: Eagle Mountain City Building Department.
- Phone: 801-789-6614, the Building Department number on the city's permit handout. The city's main line is 801-789-6600.
- Email: buildinginspections@eaglemountain.gov, which the department's building page gives for questions and inspection requests.
Rules and fees change, so call 801-789-6614 to confirm anything below before you rely on it.
Step 1: Does your deck need a permit?
The city's building page says building permits are required for all attached decks, and for any deck 30 inches or more above grade.
The permit handout describes the exemption. A deck is exempt only if it is not more than 30 inches above grade at any point and needs no guardrails, measured 36 inches out from the deck edge and then down to grade. Utah's statewide amendment agrees, and adds that the deck must not serve the exit door the code requires (Utah Code 15A-3-202).
Two wrinkles are worth knowing.
- The building page says all attached decks need a permit, while the handout describes a low-deck exemption. For a low, attached deck, the department decides which wording governs.
- The two wordings meet at exactly 30 inches: "30 inches or more" needs a permit, "not more than 30 inches" is exempt. A deck right at that height is a question for the department.
Plan on a permit unless the Building Department confirms that your deck does not need one.
Step 2: Gather the submittal
A deck permit submittal on the building page includes:
- the application
- the deck checklist
- building plans
- any required engineering
- a site plan with setback measurements
The city's deck checklist says documents go in as PDF files to the online permit portal to begin plan review. The portal address on that sheet is eaglemountainut.portal.opengov.com.
Ask the contractor who will apply. The site plan has to show setbacks, so ask the contractor to check the zone for your lot.
Step 3: Settle the engineering question
Eagle Mountain's two deck sheets word this differently.
- The deck checklist says all decks require structural engineering.
- The city's prescriptive deck requirements say decks of significant height and somewhat complex nature may require a structural engineer, and point to section R507 of the code.
Ask the contractor what engineering the quote includes, and ask the department which sheet governs your deck. The cost page lists engineering among the things that move a quote.
Step 4: Check the footing and load numbers on the plans
- The city's Building Division design criteria set frost depth at 30 inches.
- The deck checklist says plans must show footings at least 30 inches deep.
- The design criteria say the ground snow load comes from the Utah State University snow load website, and list a residential design wind speed of 100 to 105 mph. See the city's design criteria.
- Before any footing is dug, Blue Stakes of Utah 811 asks for at least 3 business days' notice of any excavation. The service is free and required by law (Blue Stakes of Utah). Ask who on the job places that request, and get confirmation that it went in.
The city enforces the 2021 International Residential Code with State amendments. Utah's code page adopts the 2021 code statewide together with state and local amendments (Utah Code 15A-2-103), so a city's rules can differ from the model code.
Step 5: Know what inspectors look at
Inspectors check structure and safety. An inspector looks at these three items, each with a rule behind it.
- Footings. Depth and size against the plan.
- The ledger. The code says a ledger may not be supported on stone or masonry veneer and must be flashed so water does not reach the house band joist (third-party copy of the code, UpCodes chapter 5).
- Guards. At least 36 inches high, no opening a 4-inch sphere can pass, needed where the drop is more than 30 inches (third-party copy of the code, UpCodes chapter 3). Eagle Mountain's prescriptive sheet says a deck that exceeds 30 inches in height must have a guard.
Stairs get measured too. Utah's maximum riser is 8 inches and its minimum tread is 9 inches. See stairs and railings.
Step 6: Schedule inspections by email
The city says all inspections must be scheduled by email, and an inspection is not scheduled until the department sends a confirmation email (building page). Ask the contractor who sends the request, and treat a time as booked only once the reply arrives.
Step 7: Know the fees
The city's consolidated fee schedule sets the building permit fee by valuation. It starts at $24 for the first $500 and adds $3 per additional $100 in the next bracket, plus a 1% state surcharge. The residential plan review fee is 40% of the permit fee.
These are the city's own fees. The total for your deck depends on its valuation, so the department or your contractor can give the figure for your project.
Step 8: Covers, roofs and pergolas
The building page also requires permits for all attached awnings and patio covers. A gazebo of 200 square feet or less with no electrical, plumbing or mechanical service needs no permit but must meet zoning. See covered decks and pergolas.
Common questions
Does a permit protect you if the work is poor?
A permit brings an inspection. It is not a promise about the contractor's work. Check the license in Utah's lookup and ask for a written agreement.
Can the contractor pull the permit?
Ask the contractor to confirm in writing who applies through the portal and who handles inspections.
How do you get matched with a contractor?
Use the contact page and give the deck height and whether it attaches to the house.
Where these numbers come from: the city pages, fee schedule and design criteria linked above, Utah Code and Blue Stakes of Utah, all read in November 2026.